November 2004 Newsletter

Regional Update on
Wind Energy in the Pacific Northwest
By Bonneville Power
Administration
Here in the Northwest
as much as 800 megawatts of new wind-generated energy could hit the region's
electrical grid by the end of 2005. Steve Enyeart, TBL customer service
engineer, says, "Planning, environment, design and construction may
be faced with some interesting challenges in the coming months if we are
going to meet the schedules proposed by the developers wanting to take
advantage of the tax credit."
Enyeart said that
the 800 MW could come from five new wind farms in Oregon and Washington
that are nearly ready to go. That could mean $500 million to $900 million
in new investment in the region.
To interconnect those
five, BPA must build three new substations, all funded by the wind developers.
"In order to meet developers' schedules, we have to begin building
those substations by next March and complete them by November," Enyeart
said. He estimated that could add up to $20 million worth of work for
BPA. Another developer has recently suggested BPA rebuild 14 miles of
the Goshen-Palisades transmission line in Idaho to connect a proposed
wind plant near Idaho Falls to PacifiCorp's system.
"All these projects
mean close coordination with our environmental staff," said Rick
Yarde, environmental protection specialist. "We're working with TBL
to streamline schedules and focus our environmental studies on the impacts
of those proposed interconnections." One way of streamlining is by
doing facilities designs and environmental studies simultaneously rather
than sequentially.
Yarde says the sudden
crush of work will be challenging as wind developers revive proposals
that have been lingering in the request queue. "Even if BPA has no
money or construction involved, we still have to study the impacts of
an interconnection," Yarde said.
In the Power Business
Line, customer account executive Debra Malin foresees an increasing number
of requests for network wind integration service and storage and shaping
services, but she says, "We're ready for such requests."
Most of the interconnection
studies are nearly complete, and environmental studies for the five Northwest
projects are underway. However, there are still transmission capacity
and operational issues. Enyeart says there is no available transmission
capacity to sell in most of the corridors serving the new wind plants.
"Nearly all these new projects will initially depend on nonfirm transmission
to get their power to market," he said. Even with the successful
completion of the proposed McNary-John Day 500-kilovolt transmission line,
additional firm transmission wouldn't be available in the primary corridor
until Spring 2007 at the earliest.
|