November 2004 Newsletter

Burley Wind Farmer
Gets $500,000 Grant
September 17, 2004
By Chip Thompson, Twin Falls Times-News
A local farmer's dream
of constructing a 10-megawatt wind farm on his Burley Butte property got
a big boost Wednesday.
LeRoy Jarolimek received
a call in the afternoon from Dale Lish, Idaho's rural energy coordinator
for the U.S. Department of Agriculture, who said Jarolimek had been awarded
a $500,000 USDA grant for the next phase of his project -- installation
of a 1.65-megawatt turbine.
The new turbine and
equipment to connect it to the power grid are expected to cost up to $2.5
million, Jarolimek said, but a private investor from the Sun Valley area
has agreed to finance the remaining amount.
"She's interested
in renewable energy and creating jobs in the agricultural area and sees
this as a tremendous opportunity for farmers," Jarolimek said, adding
that he did not want to name the investor without speaking to her first.
Jarolimek installed
a 20-kilowatt turbine May 20, which began powering his home and shop building
in early June. The turbine generates more power than he uses on average,
so he receives a check each month from Idaho Power Co. for the additional
power created.
Ultimately, Jarolimek
said he plans to install six large turbines on his property and that with
enough investment capital all six could go in next year. The towers will
stand as high as 250 feet and cost about $1.3 million each to install
once the connection to the power grid is established, he said.
"If we can put in
all the towers at the same time then it would be cheaper to install them
than doing one at a time," he said.
Much depends on passage
of production tax credits at the federal level, Jarolimek said. If tax
credits pass the project becomes much more profitable and would attract
more investors.
Under the Public Utilities
Regulatory Policy Act of 1978, Idaho electrical utilities are required
to purchase power from qualifying facilities, which include those generating
less than 10 megawatts, at set rates under 20-year contracts. The price
is based on the "avoided cost" for the utility to build and operate a
natural gas power plant.
According to the Idaho
legislature's Web site, Idaho has the highest avoided cost rate when compared
to Utah, Wyoming, Oregon and Washington.
Jarolimek said the
rate is currently at 4.5 cents per kilowatt hour but could go as high
as 7 cents. Each of the planned turbines is expected to generate 4.9 million
kilowatt hours annually, meaning that Jarolimek's farm could generate
between $1.3 million and $2 million each year for 20 years.
But Jarolimek didn't
start looking at wind power as a way to get rich. Instead, he said he
was concerned about the difficulties independent farmers faced just trying
to make a living. So a little over two years ago when his son, Ronnie,
suggested the family consider wind power at their farm, he began educating
himself on the concept and discovered wind power might be a way to help
make farming profitable for farmers and their families.
Since then he's traveled
across the state and the West attending and speaking at seminars and talking
with farmers about wind power and grants available to help them get started.
Neighbors of Jarolimek
have been supportive of the project, he said, and have told him they are
curious to see the new towers. A few of his neighbors have even begun
testing their property for wind power potential, he added.
The project is still
awaiting approval from Cassia County officials, but Jarolimek said the
county is working to make the process easier for small wind farmers by
eliminating the need for a special-use permit.
Looking to the future,
Jarolimek said he may apply for a grant to develop a new kind of turbine
uniquely suited to powering just a few homes. The design would allow a
single tower to turn separate, smaller generators that would then provide
electricity to individual homes.
NewsTracker:
• Last we knew: LeRoy
Jarolimek installed a 120-foot, 20-kilowatt wind turbine on his farm on
the Burley Butte west of town using about $30,000 in U.S. Department of
Agriculture grant money and $20,000 of his own money.
• The latest: Jarolimek
got news Wednesday that he'd been awarded a $500,000 USDA grant to help
fund installation of a 1.65-megawatt turbine on his property.
• What's next: The
new turbine, one of six Jarolimek plans to install, is expected to be
in place by next summer with the help of a private investor from the Sun
Valley area.
|